A lot was accomplished this past week. We got some good material for the Appreciation Board and we appreciate very much those who contributed to the collection. The workers are observed quite often reading the material. It is an excellent witness to everyone who walks by.
The plumbers were in and got a great deal done on the plumbing. This must be done before the concrete floor can be poured.
The electricians were also in and worked on forming and pouring concrete for the main electrical service to the building and also other electrical items.
Some of the electricians enjoying lunch Friday provided by the Hospitality Committee.
The roofers got started on roofing the foyer and are expecting to finish this coming week.
The Koreteck (white styrofoam) walls are on. The small windows (except for four in the NW corner) have been installed. The store fronts in the North and West entrances have yet to be installed. The roofers still have work to do on the area over the foyer and West and North entrances.
The big windows in the south side of the sanctuary have yet to be installed.
The small doors in the maintenance entrances have yet to be installed.
The roofers have some trim work to do over the main sanctuary and around the mansard roof.
But, we are getting very close to having the building dried in.
Please continue to pray that the weather remains good so that we can get the concrete floors poured and the building completely dried in by the end of February. This will be a big step in moving into the next phases of our building construction.